Rehabilitation of the Medium Voltage Grid in Selected Areas of Dar’a Governorate
The medium voltage grid in Dar’a Governorate has not been adequately maintained since the start of the conflict due to the lack of resources and equipment. Medium voltage hardware such as circuit breakers, underground cables, overhead conductors, fuses, poles, towers, isolators, disconnectors and other assets have been damaged or destroyed. Part of the medium voltage underground cables have become out of service due to a lack of maintenance and i...

Complementary Project for Enhancing Food Security in Dar’a and Quneitra Governorates
The South of Syria has seen a significant population growth since July 2017 when de-escalation of the conflict and ceasefire came to an effect. Consequently, demand for subsistence foodstuff, especially bread, has increased significantly, putting heavy pressure on a food security system that was already weakened by years of fighting since the start of the conflict in 2011. The governorates of Dar’a and Quneitra currently suffers from insufficient...

Support to Health Services in Dar'a Governorate
Before the outbreak of conflict in Syria, the mainstream health services were provided by the public sector. The private sector’s health services were supplementary to those of the public sector. Critical health services were centralized in Damascus and in the capital city of each governorate. Since the start of the conflict, local medical groups (i.e. doctors, nurses and paramedical staff) have attempted to provide alternative health services....

Rehabilitation and Maintenance of High voltage Grid in Selected Areas of Aleppo Governorate
Since the start of the conflict and due to the lack of resources, the equipment of the high voltage transmission has not been sufficiently maintained and is at a high risk of failure for some areas in Aleppo Governorate. Without the planned preventive maintenance of the high voltage sub-stations there are frequent break-downs, which result in major power outages for a large number of households and other consumers. One of the main infrastructur...

Rehabilitation of the Medium Voltage Grid in Selected Areas of Dar’a Governorate
The medium voltage grid in Dar’a Governorate has not been adequately maintained since the start of the conflict due to the lack of resources and equipment. Medium voltage hardware such as circuit breakers, underground cables, overhead conductors, fuses, poles, towers, isolators, disconnectors and other assets have been damaged or destroyed. Part of the medium voltage underground cables have become out of service due to a lack of maintenance and i...

Complementary Project for Enhancing Food Security in Dar’a and Quneitra Governorates
The South of Syria has seen a significant population growth since July 2017 when de-escalation of the conflict and ceasefire came to an effect. Consequently, demand for subsistence foodstuff, especially bread, has increased significantly, putting heavy pressure on a food security system that was already weakened by years of fighting since the start of the conflict in 2011. The governorates of Dar’a and Quneitra currently suffers from insufficient...

Support to Health Services in Dar'a Governorate
Before the outbreak of conflict in Syria, the mainstream health services were provided by the public sector. The private sector’s health services were supplementary to those of the public sector. Critical health services were centralized in Damascus and in the capital city of each governorate. Since the start of the conflict, local medical groups (i.e. doctors, nurses and paramedical staff) have attempted to provide alternative health services....

Rehabilitation and Maintenance of High voltage Grid in Selected Areas of Aleppo Governorate
Since the start of the conflict and due to the lack of resources, the equipment of the high voltage transmission has not been sufficiently maintained and is at a high risk of failure for some areas in Aleppo Governorate. Without the planned preventive maintenance of the high voltage sub-stations there are frequent break-downs, which result in major power outages for a large number of households and other consumers. One of the main infrastructur...